share this

Share This Search
News
View full story holidaycardrawley.jpg

Story: Dec 17, 2014

Students animate, illustrate holiday greetings on behalf of ...

View details 35th Annual Scholastic Art & Writing Exhibition

CIA Exhibition: Jan 14, 2015

35th Annual Scholastic Art & Writing Exhibition

View full story madesurrealvictoriabest4041.jpg

Story: Nov 15, 2014

Students capture two of the top prizes in museum's surreal d...

View details 69th Annual Student Independent Exhibition

CIA Exhibition: Feb 13, 2015

69th Annual Student Independent Exhibition

View Link

Social: a day ago via Facebook

Warm wishes to you this holiday season from the Cleveland Institute of Art! Artwork created by Animation majors Brienne Broyles 16 and Maria Ursetti 16. Rea...

View full story dsc92052.jpg

Story: Nov 04, 2014

New CIA building taking shape; set for December completion

View details Spring 2015 Open House

Events: Mar 21, 2015

Spring 2015 Open House

View full story unknown.png

Story: Nov 03, 2014

New Uptown Residence Hall featured in CIA video

News . Feature Stories . Campus Project Update ? July '09

News

July 24, 2009

Campus Project Update ? July '09

Construction crews spent June and July 2009 renovating major parts of the McCullough Center, especially its heating and cooling systems.

Campus Project Update ? July '09

It’s been a busy summer at the Institute’s Joseph McCullough Center for the Visual Arts, where considerable progress has already been made on our enormously important campus modernization and unification project. Construction crews are renovating the McCullough building, which was originally built in 1914 as a Model T Ford assembly plant. That facility, which the Institute has now owned for a quarter of a century, will serve as the core of the new, unified campus. But first it needs to undergo major repairs and updating, particularly to make its heating and cooling systems more effective and energy efficient and to better utilize existing space within the building.

Toward those ends, over the last two months:

• Air handling units have been installed on all four floors

• Three 200-ton capacity centrifugal chillers have been moved into place

• A cooling tower has been placed on the roof

• Four hot water heating boilers have been moved into place to keep the building warm during the winter months

• Three domestic hot water heating boilers have been installed to supply the building’s hot water

• Installation of duct work has been initiated; in some areas, temporary duct work will be used to assure cooling until permanent duct work can be put in place

• The east and north sides of the building have been power washed to help refresh the appearance of the historic building

• Masonry repairs on the east and north sides of the building are well underway, which will safeguard against the infiltration of water into the building and prevent the recurrence of leaks

• Multiple layers of existing roofing have been removed and a new rubber membrane has been installed, held down by heavy river-bed stone, to prevent leakage from the roof

• The third floor has been extended out over the Sculpture area (which used to be two floors high), thus creating nearly 5,500 square feet of new space that will be used for instructional and studio purposes as well as for installation projects (shown in picture)

• The large first floor space, formerly leased to the Social Security Administration, is being transformed into six academic classrooms and a new home for the Academic Writing Center

—Courtesy of David Deming, President of The Cleveland Institute of Art

Read more campus project updates.

YouTube Facebook Twitter LinkedIn Flickr Pinterest Instagram

Social Feed

Warm wishes to you this holiday season from the Cleveland Institute of Art! https://t.co/sWhJEIOEW3

a day ago via Twitter

Questions?

For more information about this or other CIA news, contact us here.

Read More

Community Works

Visiting artists, exhibitions, conference and symposia exploring socially engaged art.

Read More

Uptown Residence Hall

Check out the new student digs.

Read More

Cores + Connections

Creating. Connecting. Building better futures.